LOCAL 48 ELECTRICIANS PAC: Alleged violations of RCW 42.17A.250 for failure to timely and accurately report as an out-of-state political committee (EY24 AUG24)

Case

#158465

Respondent

LOCAL 48 ELECTRICIANS PAC - Oregon

Complainant

Conner Edwards

Description

PDC staff reviewed the allegations and evidence you submitted; the applicable statutes, rules, and reporting requirements; the response(s) provided by the Local 48 Electricians PAC (the “Respondent”); the applicable PDC reports filed by the Respondent; and other relevant information, to determine whether the record supports a finding of one or more violations.
 

Applicable Laws & Rules

Under RCW 42.17A.250(2), an out-of-state political committee is required to file an Out-Of-State Political Committee (C-5) Report “no later than the tenth day of the month following any month in which a contribution or other expenditure reportable under subsection (1) of this section is made.  An out-of-state committee incurring an obligation to file additional statements in a calendar year may satisfy the obligation by timely filing reports that supplement previously filed information.”

Background & Findings

Based on staff’s review, we found the following:

• The Local 48 Electricians Political Action Committee (PAC) is a political action committee of the International Brotherhood of Electrical Workers, Local 48 union, based in Portland, Oregon.
• Local 48 Electricians PAC receives contributions from Washington residents.  The PAC expends those funds by being the primary contributor to the Southwest WA Electricians PAC 48 of WA, a Washington state registered political action committee.  The Southwest WA Electricians PAC participates in Washington elections by contributing to candidates and other committees.  These two PACs share the same stated purpose of supporting candidates and measures advocating family, living wages, benefits and working conditions.
• On September 25, 2024, the Local 48 Electricians PAC filed three Out-of-State Political Committee (C-5) reports with the Washington State Public Disclosure Commission (PDC) for 2024.  The reports were amended on October 3rd, 4th and 7th in 2024 and included expenditures to Southwest WA Electricians PAC 48 of WA for a total of $110,839.02 between February and September 2024.
o These reports also showed a total of $251,278.77 reported as contributions received from Washington state residents.
o The September report was timely, but the reports covering earlier periods in the year were untimely.
• On September 25, 2024, the Local 48 Electricians PAC filed four C-5 reports with the PDC for 2023.  The reports were amended on October 10, 2024, and included expenditures to Southwest WA Electricians PAC 48 of WA for a total of $71,116.99 between January and September 2023.
o These reports also showed a total of $194,193.90 reported as contributions received from Washington state residents.
o All the reports were filed late.
• On October 18, 2024, the Local 48 Electricians PAC filed the following C-5 reports with the PDC:
o Four C-5 reports were filed for 2022.  The reports showed expenditures to Southwest WA Electricians PAC 48 of WA for: $21,701.61 on February 11, 2022; $32,368.75 on June 1, 2022; $36,943.95 on September 1, 2022; and $38,335.22 on November 17, 2022.
o All the reports were filed late.
• On October 29, 2024, the Local 48 Electricians PAC filed the following C-5 reports with the PDC:
o Eight C-5 reports were filed for 2021 and are late filed.  The reports showed expenditures to Southwest WA Electricians PAC 48 of WA for: $22,425.09 on January 25, 2021; $11,998 on February 22, 2021; $9,936.36 on March 30, 2021; $21,058.22 on May 17, 2021; $23,419.74 on July 30, 2021; $10,610.03 on September 8, 2021; $11,609.93 on October 15, 2021; and $36,116.28 on December 8, 2021.
o Six C-5 reports were filed for 2020 and are late filed.  The reports showed expenditures to Southwest WA Electricians PAC 48 of WA for: $32,008.32 on January 6, 2020; $20,678.12 on March 2, 2020; $10,308.66 on April 16, 2020; $21,475.84 on June 10, 2020; $20,466.20 on August 28, 2020; and $30,439.61 on November 10, 2020.
o Nine C-5 reports were filed for 2019 and are late filed.  The reports identified expenditures to Southwest WA Electricians PAC 48 of WA for: $10,402.15 on January 22, 2019; $10,562.58 on February 21, 2019; $9,443.32 on March 14, 2019; $9,890.63 on April 11, 2019; $11,739.11 on May 7, 2019; $10,217.72 on June 26, 2019; $50,000 on July 3, 2019; $32,124.85 on September 6, 2019; and $11,828.06 on October 14, 2019.
• The Respondent does not have previous warnings or violations of similar PDC requirements.

Summary and Resolution

The Local 48 Electricians PAC completed a Statement of Understanding (SOU) and paid a $750 civil penalty in accordance with WAC 390-37-143 (Brief Enforcement Penalty Schedule), acknowledging a violation of RCW 42.17A.250 for failing to timely and accurately report as an out-of-state political committee in years 2019, 2020, 2021, 2022, 2023, and 2024. The $750 penalty assessed resolves the allegations listed in your complaint.

Based on this information, the PDC finds that no further action is warranted and has dismissed this matter in accordance with RCW 42.17A.755(1).

Disposition

Resolved through Statement of Understanding (SOU)

Date Opened

August 21, 2024

Areas of Law

RCW 42.17A.250

Penalties

Total penalties: $750

Balance Due: $0

LOCAL 48 ELECTRICIANS PAC

Penalty
$750 (Statement of Understanding)
Payments
$750 on 11/14/2024 (PAID - SOU)

Subscribe for updates


{{statusMessage}}

To subscribe to this case, enter your email address in the form below and click "Send confirmation link" button. You will be sent a secure link via email that will confirm your subscription.


An email containing a link to confirm your subscription to this case has been sent to {{ email }}.

If you do not receive an email within a few minutes, please check your junk mail or mail filters.

Send again

{{statusMessage}}